📞 0339-0387701 (WhatsApp)
Contact
☰
🔍
Home
Important MCQs
Computer
Current Affairs
Data Science & AI (NCCIA)
Database & Data Handling (NCCIA)
English
Everyday Science
General Knowledge
General Science
Information & Networking (NCCIA)
Islamic Studies MCQs
Maths MCQs
Pak Study
Pedagogy
Software Engineering (NCCIA)
Telecom / Electrical Fundamentals (NCCIA)
Urdu MCQs
Past Papers
ASF Past Papers
FIA Past Papers
FPSC Past Papers
NCCIA Past Papers
NTS Past Papers
PPSC Past Papers
Latest Jobs
Army Jobs
Education Department
Federal Govt Jobs
Health Department
Police Jobs
Sindh Govt Jobs
Resources
About Us
Contact
🔍
Home
» Which strategy eliminates a risk by changing the project plan?
« Back to Software Engineering (NCCIA)
Which strategy eliminates a risk by changing the project plan?
A. Mitigation
B. Avoidance ✅
C. Acceptance
D. Transference
Correct Answer:
B. Avoidance
Explanation
Avoidance removes the threat, for example by dropping a risky feature or changing technology
The risk can no longer occur.
« Transferring a risk to a third party, for example by…
Mitigation of a risk means what? »
Related MCQs
In an activity diagram, what is an object node?
What is an emergency change?
If project scope increases without extra time or budget, what is likely to happen?
Which quality attribute describes how well a system performs under load?
Which document usually contains system requirements?
In CPM, what is a forward pass used to calculate?
What is the main difference between Scrum and Kanban?
In the V-model, acceptance testing corresponds to which phase?