If project scope increases without extra time or budget, what is likely to happen?

A. Cost will fall
B. Quality or schedule will suffer ✅
C. Nothing will change
D. The project will finish early

Correct Answer: B. Quality or schedule will suffer

Explanation

  • More work with the same resources strains the project
  • Trade-offs are unavoidable.