In CPM, what is a forward pass used to calculate?

A. Early start and early finish ✅
B. Late start and late finish
C. Total cost
D. Resource needs

Correct Answer: A. Early start and early finish

Explanation

  • The forward pass moves left to right to find earliest dates
  • The backward pass finds latest dates.