📞 0339-0387701 (WhatsApp)
Contact
☰
🔍
Home
Important MCQs
Computer
Current Affairs
Data Science & AI (NCCIA)
Database & Data Handling (NCCIA)
English
Everyday Science
General Knowledge
General Science
Information & Networking (NCCIA)
Islamic Studies MCQs
Maths MCQs
Pak Study
Pedagogy
Software Engineering (NCCIA)
Telecom / Electrical Fundamentals (NCCIA)
Urdu MCQs
Past Papers
ASF Past Papers
FIA Past Papers
FPSC Past Papers
NCCIA Past Papers
NTS Past Papers
PPSC Past Papers
Latest Jobs
Army Jobs
Education Department
Federal Govt Jobs
Health Department
Police Jobs
Sindh Govt Jobs
Resources
About Us
Contact
🔍
Home
» In CPM, what is a forward pass used to calculate?
« Back to Software Engineering (NCCIA)
In CPM, what is a forward pass used to calculate?
A. Early start and early finish ✅
B. Late start and late finish
C. Total cost
D. Resource needs
Correct Answer:
A. Early start and early finish
Explanation
The forward pass moves left to right to find earliest dates
The backward pass finds latest dates.
« What is the earliest finish of an activity starting day…
In CPM, what is a backward pass used to calculate? »
Related MCQs
A race condition is most likely to occur in which situation?
What is a functional requirement in an SRS?
What is the main purpose of a requirements review checklist based on IEEE 830?
Smoke testing is:
What is functional testing?
In an ERD, a diamond represents:
Which is a benefit of prototyping for communication?
What is verification in software engineering?