What is the exit criterion for testing?

A. A condition that must be met before testing can be considered complete ✅
B. The project budget
C. The start date of testing
D. The number of developers

Correct Answer: A. A condition that must be met before testing can be considered complete

Explanation

  • Exit criteria include test coverage and defect thresholds
  • They decide when testing can stop.