📞 0339-0387701 (WhatsApp) Contact

« Back to Software Engineering (NCCIA)

Why is the iterative model called a risk-driven approach in practice?

A. Because it never tests
B. Because each cycle tests assumptions before more investment ✅
C. Because it avoids all risks
D. Because it has no plan

Correct Answer: B. Because each cycle tests assumptions before more investment

Explanation

Each iteration is a checkpoint that can reveal problems early, limiting the amount invested before learning.