A project has unclear requirements and the client expects frequent changes. Why is Waterfall a poor choice?

A. Because it has no testing phase
B. Because it assumes requirements are known early and are stable ✅
C. Because it delivers software too early
D. Because it needs no documentation

Correct Answer: B. Because it assumes requirements are known early and are stable

Explanation

Waterfall's core assumption is fixed early requirements; changing needs break it.