What is the critical path in project scheduling?

A. The path with the most team members
B. The longest sequence of dependent tasks that determines the shortest possible project duration ✅
C. The shortest path through the project
D. The path with the lowest cost

Correct Answer: B. The longest sequence of dependent tasks that determines the shortest possible project duration

Explanation

  • Delay on the critical path delays the whole project
  • It has zero float.