A project delivers on time but the system does not do what users need. According to SDLC quality thinking, the project has failed in what respect?

A. Effectiveness, because it did not achieve its purpose despite meeting the schedule ✅
B. Cost only
C. No respect, on time is all that matters
D. Efficiency only, because it was too fast

Correct Answer: A. Effectiveness, because it did not achieve its purpose despite meeting the schedule

Explanation

Success is judged by meeting user needs and objectives, not only by time and budget.