Which project should AVOID the V-model?

A. A project with rapidly changing requirements and an unknown final scope ✅
B. A medical imaging system
C. A safety-critical avionics system
D. A fixed-specification defence system

Correct Answer: A. A project with rapidly changing requirements and an unknown final scope

Explanation

The V-model's rigidity makes it a poor fit when requirements evolve frequently.