Which of the following is one of the twelve principles of Agile?

A. Avoid customer contact until delivery
B. Freeze all requirements after the first week
C. Welcome changing requirements, even late in development ✅
D. Deliver software only once at the end

Correct Answer: C. Welcome changing requirements, even late in development

Explanation

Agile Principle 2 states that changing requirements should be welcomed, even late in development, for the customer's competitive advantage.