Which change should normally be rejected or deferred?

A. A change that corrects an error in the SRS
B. A change that fixes a critical safety defect
C. A change required by a new law
D. A change with high cost and risk but low business value ✅

Correct Answer: D. A change with high cost and risk but low business value

Explanation

  • Change decisions weigh value against cost and risk
  • Low-value, high-cost changes are poor investments.