What is the relationship between WBS and cost estimation?

A. No relationship
B. Cost is estimated only at the top level
C. Cost estimates are built bottom-up by estimating each work package and summing them ✅
D. Cost estimation replaces the WBS

Correct Answer: C. Cost estimates are built bottom-up by estimating each work package and summing them

Explanation

  • Each work package is estimated, then rolled up to give the project cost
  • This is bottom-up estimating.