What is the top level of a WBS hierarchy?

A. Work package
B. Project deliverable
C. Task list
D. Final project or product ✅

Correct Answer: D. Final project or product

Explanation

  • The top level is the total project or final product
  • It is then decomposed into phases, deliverables and work packages.