In Kanban, how is new work started?

A. Only after a full release
B. When capacity becomes available, as signalled by a WIP limit, work is pulled into the workflow ✅
C. Only when the manager orders it
D. Only at the start of a monthly Sprint

Correct Answer: B. When capacity becomes available, as signalled by a WIP limit, work is pulled into the workflow

Explanation

Kanban is a pull system: work is pulled into a stage only when there is free capacity, unlike push systems that assign work regardless of load.