📞 0339-0387701 (WhatsApp) Contact

« Back to Software Engineering (NCCIA)

What is the difference between a project plan and a project schedule?

A. They are identical
B. There is no project plan
C. The plan covers all aspects; the schedule is the timing of tasks only ✅
D. The schedule covers all aspects; the plan is timing only

Correct Answer: C. The plan covers all aspects; the schedule is the timing of tasks only

Explanation

  • A plan includes scope, cost, quality, and risk
  • A schedule focuses on task timing.