What is a project baseline?

A. The first draft of a plan
B. The final project report
C. The approved plan for scope, schedule, and cost against which performance is measured ✅
D. A list of risks

Correct Answer: C. The approved plan for scope, schedule, and cost against which performance is measured

Explanation

  • Baselines are the reference for measuring progress
  • Changes need formal approval.