What is a baseline change?

A. A change with no effect
B. A change to a draft only
C. A change to an approved baseline, requiring formal approval ✅
D. A change to a test case only

Correct Answer: C. A change to an approved baseline, requiring formal approval

Explanation

  • Baselines are controlled reference points
  • Changing them needs formal change control.