Planning comes before requirements analysis because:

A. Testing must be done first
B. Users must be trained first
C. The project must be shown feasible and scoped before detailed analysis begins ✅
D. Code must be written first

Correct Answer: C. The project must be shown feasible and scoped before detailed analysis begins

Explanation

Feasibility and scope decisions in planning prevent wasted analysis on an unviable project.