A Gantt chart in SDLC planning is used to show what?

A. Tasks, their durations and their sequence over time ✅
B. The internal code structure
C. The user interface layout
D. The database schema

Correct Answer: A. Tasks, their durations and their sequence over time

Explanation

A Gantt chart visualises the project schedule, showing when each task starts, ends and overlaps.