📞 0339-0387701 (WhatsApp) Contact

« Back to Maths MCQs

60 man can do a work in 40 days. How long will it take 40 men to complete the same work?

A. 60 days ✅
B. 30 days
C. 29 days
D. 23 days

Correct Answer: A. 60 days

Explanation

  • Men days
  • 60 : 40
  • 40 : x
  • 60/40= x/40, 40x= 60* 40
  • x= 40*60/40, x= 60