15 men can work a do in 12 days. How long it will take 9 men to do work?

A. 20 ✅
B. 14
C. 9
D. None of these

Correct Answer: A. 20

Explanation

  • If 15 men can complete the work in 12 days,
  • it means that the total number of man-days required to complete the work is:
  • 15 men * 12 days = 180 man-days.
  • 180 man-days / 9 men = 20 days.