Which of the following is the best time to validate requirements?

A. Only during acceptance testing
B. Only after the system is delivered
C. As soon as they are drafted, before design and coding begin, and again after changes ✅
D. After the project is closed

Correct Answer: C. As soon as they are drafted, before design and coding begin, and again after changes

Explanation

  • Early validation is cheapest
  • Re-validation after change prevents new errors entering the baseline.