Which of the following is a sign that requirements validation was skipped?

A. The code has no comments
B. The SRS is too long
C. The project finishes early
D. Users reject the delivered system because it does not do what they need ✅

Correct Answer: D. Users reject the delivered system because it does not do what they need

Explanation

  • Unvalidated requirements often miss the real need
  • Rejection at acceptance is the classic symptom.