📞 0339-0387701 (WhatsApp)
Contact
☰
🔍
Home
Important MCQs
Computer
Current Affairs
Data Science & AI (NCCIA)
Database & Data Handling (NCCIA)
English
Everyday Science
General Knowledge
General Science
Information & Networking (NCCIA)
Islamic Studies MCQs
Maths MCQs
Pak Study
Pedagogy
Software Engineering (NCCIA)
Telecom / Electrical Fundamentals (NCCIA)
Urdu MCQs
Past Papers
ASF Past Papers
FIA Past Papers
FPSC Past Papers
NCCIA Past Papers
NTS Past Papers
PPSC Past Papers
Latest Jobs
Army Jobs
Education Department
Federal Govt Jobs
Health Department
Police Jobs
Sindh Govt Jobs
Resources
About Us
Contact
🔍
Home
» Which dependency type means Task B cannot start until Task A finishes?
« Back to Software Engineering (NCCIA)
Which dependency type means Task B cannot start until Task A finishes?
A. Start-to-start
B. Start-to-finish
C. Finish-to-finish
D. Finish-to-start ✅
Correct Answer:
D. Finish-to-start
Explanation
Finish-to-start is the most common dependency
B starts only after A ends.
« What is a dependency in project scheduling?
What does PERT stand for? »
Related MCQs
Scalability testing checks whether the system can handle what?
In the spiral model, risk resolution may involve:
A milestone in SDLC planning differs from a task in that a milestone does what?
Which document records the results of test execution?
Microservices architecture divides a system into:
What is a breakpoint in debugging?
If HLD is skipped and coding starts directly from requirements, the likely result is:
Which Waterfall phase is MOST likely to reveal that the technology chosen cannot meet performance needs?