Which change should normally be rejected?

A. A change with clear benefit and low cost
B. A change with high cost, high risk and little benefit ✅
C. A change requested by the client
D. A change that fixes a fault

Correct Answer: B. A change with high cost, high risk and little benefit

Explanation

  • The CCB weighs benefit against cost and risk
  • Low-value, high-risk changes are rejected or deferred.