What is the main drawback of a very large Sprint Backlog?

A. It improves focus
B. It reduces risk
C. It speeds up delivery
D. It makes the Sprint Goal unclear and increases the risk that the team will not finish the work ✅

Correct Answer: D. It makes the Sprint Goal unclear and increases the risk that the team will not finish the work

Explanation

Overcommitting a Sprint spreads the team thin, so a focused, realistic Sprint Backlog is more likely to deliver a Done increment.