What is secondary risk?

A. A risk created as a direct result of implementing a risk response ✅
B. A risk in a second project
C. A low-priority risk
D. A risk with no owner

Correct Answer: A. A risk created as a direct result of implementing a risk response

Explanation

  • For example, adding a new tool to mitigate a risk may introduce a learning-curve risk
  • Secondary risks need their own responses.