What is rolling wave planning in relation to WBS?

A. Planning all details at project start and never changing them
B. Using waves to test software
C. Planning only after the project ends
D. Planning near-term work in detail and future work at a higher level until more information is available ✅

Correct Answer: D. Planning near-term work in detail and future work at a higher level until more information is available

Explanation

  • Rolling wave planning progressively elaborates the WBS as uncertainty reduces
  • Near work is detailed, distant work is summary-level.