What is project scope?

A. The project schedule only
B. The team members only
C. The work that must be done to deliver the project's product, including what is included and excluded ✅
D. The project budget only

Correct Answer: C. The work that must be done to deliver the project's product, including what is included and excluded

Explanation

  • Scope defines boundaries
  • It prevents uncontrolled expansion of work.