What is bottom-up estimating?

A. Estimating by team size only
B. Copying another project's budget
C. Estimating the whole project in one figure
D. Estimating each work package in detail and adding them up ✅

Correct Answer: D. Estimating each work package in detail and adding them up

Explanation

  • Bottom-up is detailed and more accurate
  • It takes longer to prepare.