What is a Gantt chart used for?

A. Showing the organisation chart
B. Showing the code structure
C. Showing project tasks, durations, and schedule on a timeline ✅
D. Showing the database design

Correct Answer: C. Showing project tasks, durations, and schedule on a timeline

Explanation

  • A Gantt chart displays tasks as bars over time
  • It shows start, finish, and overlaps.