What is a corrective action in project monitoring?

A. An action to stop the project
B. An action to ignore a problem
C. An action to change the plan without approval
D. An action taken to bring project performance back in line with the plan ✅

Correct Answer: D. An action taken to bring project performance back in line with the plan

Explanation

  • Corrective action addresses the cause of a deviation
  • Example: adding resources or re-planning a task.