What happens if a WBS omits a major deliverable?

A. The project finishes faster with no effect
B. Scope, cost and schedule estimates will be incomplete and the project may overrun ✅
C. The team gets a bonus
D. Testing becomes easier

Correct Answer: B. Scope, cost and schedule estimates will be incomplete and the project may overrun

Explanation

  • Estimates are built from the WBS
  • Missing work means missing cost, time and resources.