Schedule feasibility asks which question?

A. Is the project legally allowed?
B. Will the system make a profit?
C. Can the system be delivered within the required time frame? ✅
D. Can the hardware run the software?

Correct Answer: C. Can the system be delivered within the required time frame?

Explanation

Schedule feasibility checks whether deadlines are realistic given resources and scope.