Schedule feasibility asks whether:

A. The code is efficient enough
B. The system is legally compliant
C. The project can be completed within the available time ✅
D. The users like the interface design

Correct Answer: C. The project can be completed within the available time

Explanation

Schedule feasibility checks if deadlines are realistic given resources and constraints.