In the V-model, the shape V represents what relationship?

A. Two teams working in parallel on the same code
B. Requirements going up and down in priority
C. Each development phase on the left has a corresponding testing phase on the right ✅
D. The project cost rising then falling

Correct Answer: C. Each development phase on the left has a corresponding testing phase on the right

Explanation

The left arm is verification (development), the right arm is validation (testing).