In Scrum, what happens if the Sprint Goal becomes obsolete during a Sprint?

A. Only the Product Owner may cancel the Sprint, and cancellation is rare and costly ✅
B. The Sprint is extended
C. The team ignores the change
D. Any Developer may cancel it

Correct Answer: A. Only the Product Owner may cancel the Sprint, and cancellation is rare and costly

Explanation

A Sprint can be cancelled only by the Product Owner if the Sprint Goal becomes obsolete, for example when company direction changes.