In Kanban, what happens when a column reaches its WIP limit?

A. No new work can enter that column until an item leaves it ✅
B. The limit is ignored
C. The board is deleted
D. The team must work faster

Correct Answer: A. No new work can enter that column until an item leaves it

Explanation

A WIP limit is a hard cap: when a column is full, the team must finish or move work before pulling in more.