In EVM, what is Earned Value (EV)?

A. The total cost at completion
B. The money actually spent
C. The planned budget
D. The budgeted cost of work actually completed by a given date ✅

Correct Answer: D. The budgeted cost of work actually completed by a given date

Explanation

  • EV measures work done in budget terms
  • It is also called budgeted cost of work performed.