In a WBS, what does the term scope baseline include?

A. Only the schedule
B. Project scope statement, WBS and WBS dictionary ✅
C. Only the budget
D. The risk register

Correct Answer: B. Project scope statement, WBS and WBS dictionary

Explanation

  • The scope baseline is the approved scope statement plus WBS plus dictionary
  • Changes require formal change control.