📞 0339-0387701 (WhatsApp)
Contact
☰
🔍
Home
Important MCQs
Computer
Current Affairs
Data Science & AI (NCCIA)
Database & Data Handling (NCCIA)
English
Everyday Science
General Knowledge
General Science
Information & Networking (NCCIA)
Islamic Studies MCQs
Maths MCQs
Pak Study
Pedagogy
Software Engineering (NCCIA)
Telecom / Electrical Fundamentals (NCCIA)
Urdu MCQs
Past Papers
ASF Past Papers
FIA Past Papers
FPSC Past Papers
NCCIA Past Papers
NTS Past Papers
PPSC Past Papers
Latest Jobs
Army Jobs
Education Department
Federal Govt Jobs
Health Department
Police Jobs
Sindh Govt Jobs
Resources
About Us
Contact
🔍
Home
» If actual cost is greater than earned value, what does it mean?
« Back to Software Engineering (NCCIA)
If actual cost is greater than earned value, what does it mean?
A. The project is under budget
B. The project is ahead of schedule
C. The project is over budget ✅
D. The project is on budget
Correct Answer:
C. The project is over budget
Explanation
Actual cost above earned value means spending more than the work is worth
The project is over budget.
« If earned value is less than planned value, what does…
What is a project risk? »
Related MCQs
Use case testing is based on what?
What is horizontal prototyping?
In the V-model, when are test plans for system testing created?
What is a use case?
What is a defect (bug)?
Test coverage measures:
Which estimation approach breaks the work into small tasks, estimates each, and adds them up?
Requirements analysis must precede design because: