If Activity A takes 3 days, B takes 5 days after A, and C takes 2 days in parallel with B, what is the project duration?

A. 5 days
B. 7 days
C. 10 days
D. 8 days ✅

Correct Answer: D. 8 days

Explanation

  • Path A→B = 3+5 = 8 days; path A→C = 3+2 = 5 days
  • The longest path, 8 days, is the duration.