If a task on the critical path is delayed by five days and no other change is made, what happens to the project finish date?

A. It is delayed by five days ✅
B. It is unchanged
C. It is delayed by ten days
D. It is brought forward by five days

Correct Answer: A. It is delayed by five days

Explanation

  • By definition, the critical path has no slack
  • a delay there moves the project end by the same amount.