If 15 men can do a piece of work in 20 days. In how many days can 25 men finish the same work?

A. 14
B. 12 โœ…
C. 18
D. 13

Correct Answer: B. 12

Explanation

  • 15 men ร— 20 days = 300 man-days (total work)
  • Now, with 25 men:
  • 300 man-days รท 25 men = 12 days