How does the prototype model compare with the waterfall model?

A. Waterfall shows a prototype first
B. They are identical
C. Prototyping shows a working version early; waterfall shows the working system only at the end ✅
D. Prototyping shows nothing early

Correct Answer: C. Prototyping shows a working version early; waterfall shows the working system only at the end

Explanation

Early visibility is the prototype model's main contrast with the waterfall's late delivery.