Finish-to-start dependency means what?

A. The successor starts before the predecessor
B. The successor task cannot start until the predecessor finishes ✅
C. The tasks are unrelated
D. The tasks run at the same time

Correct Answer: B. The successor task cannot start until the predecessor finishes

Explanation

  • Finish-to-start is the standard dependency
  • It enforces sequence.