After a change request is assessed and approved, what is the next step in change management?

A. Update the affected baselines, plans and traceability records ✅
B. Delete the original requirement
C. Stop all testing immediately
D. Ignore the approved change

Correct Answer: A. Update the affected baselines, plans and traceability records

Explanation

Approved changes are implemented and the baselines, documents and traceability are updated so the change stays controlled.