A Waterfall project is halfway through coding when the client changes a core business rule. What is the MOST likely consequence?

A. The project finishes early
B. The change is free
C. Significant rework in design and code, plus schedule and cost impact ✅
D. A minor change with no effect

Correct Answer: C. Significant rework in design and code, plus schedule and cost impact

Explanation

A frozen design and code base must be revisited, so a late core change is expensive.