📞 0339-0387701 (WhatsApp)
Contact
☰
🔍
Home
Important MCQs
Computer
Current Affairs
Data Science & AI (NCCIA)
Database & Data Handling (NCCIA)
English
Everyday Science
General Knowledge
General Science
Information & Networking (NCCIA)
Islamic Studies MCQs
Maths MCQs
Pak Study
Pedagogy
Software Engineering (NCCIA)
Telecom / Electrical Fundamentals (NCCIA)
Urdu MCQs
Past Papers
ASF Past Papers
FIA Past Papers
FPSC Past Papers
NCCIA Past Papers
NTS Past Papers
PPSC Past Papers
Latest Jobs
Army Jobs
Education Department
Federal Govt Jobs
Health Department
Police Jobs
Sindh Govt Jobs
Resources
About Us
Contact
🔍
Home
» A risk with high probability and high impact should be given what priority?
« Back to Software Engineering (NCCIA)
A risk with high probability and high impact should be given what priority?
A. Lowest priority
B. Ignored
C. Highest priority ✅
D. Deferred to closure
Correct Answer:
C. Highest priority
Explanation
High probability × high impact gives the highest exposure
Such risks need urgent response planning.
« What does risk monitoring and control involve?
Which document is updated when a new risk is found… »
Related MCQs
In an RTM, a requirement with no linked test case indicates:
What is the main purpose of a software project plan?
What is accessibility in software design?
Use case testing is a black-box technique based on what?
What is a risk trigger?
A build is:
Reusing a tested library module during coding mainly helps by:
What is a common risk of evolutionary prototyping?