A project manager identifies that a key developer may leave mid-project. The appropriate SDLC response is what?

A. Record the risk, plan mitigation such as documentation and knowledge sharing, and monitor it ✅
B. Cancel the project immediately
C. Remove all documentation
D. Ignore it and hope it does not happen

Correct Answer: A. Record the risk, plan mitigation such as documentation and knowledge sharing, and monitor it

Explanation

Risk management means identifying, assessing and planning responses to risks, not ignoring them.